1 Purpose
Plastic track, artificial grass construction process and service process for effective control, to ensure the quality of the project and to meet the needs and expectations of the contract and the owners of beautification effect. At the same time ensure that the construction process, environmental management and occupational health and safety management, ecological and social benefits. The resulting output can not be confirmed by the subsequent detection process and the implementation of the control, to ensure that the process in the effective control.

2 Scope
This procedure applies to the management and control of the plastic track, artificial lawn and sports facilities such as the whole construction process.

3 Responsibilities

3.1 Engineering Department is responsible for the construction and services run the program the whole process of supervision, inspection, service work; responsible for the construction of production processes and services running technical preparation and technical support, and for the construction and production processes and services running quality management and environmental management, Occupational Health and Safety management Guidelines for the preparation of the construction organization design, quality plan, schedule, quality inspection program, and supervision and inspection.

3.2 Purchasing Department is responsible for the the synthetic grass procurement.

3.3 Project Department of the organization responsible for the program implementation.